Instructions for importing costs from timberline
1) Create Timberline report layout with the following columns in the following order
      1) Description
      2) Quantity
      3) UM
      4) Labor
      5) Material
      6) Subcontractor
      7) Equipment
      8) Bid_item
      9) Scope
2) Export layout to excel file
3) Delete headings, footings, rows with blank description
4) Add project id column and fill with project identity
5) Add order column. Start numbering at 1
6) Paste result into SQL editor
7) Press Import costs from timberline button
8) Assign each timberline scope to correct bidday scope
9) Press Update costs to scopes button